Completion of the Connection Works for the Newly Constructed Pipeline Section of the «Uzen-Atyrau-Samara» Main Oil Pipeline, Measuring 782 Meters

 24.09.2024    84
At the Atyrau oil pipeline management of KazTransOil JSC, the works to connect the newly constructed pipeline section, measuring 782 meters, to the «Uzen-Atyrau-Samara» main oil pipeline at the 1173 km mark have been successfully completed.
According to the production plan, 72 hours were allocated for the connection of the section. All technical works were completed on time, adhering to the requirements of industrial safety and labor protection.

A total of 167 specialists were involved in the works: 146 were company employees, and 21 were representatives from the contracting organization, along with 62 units of equipment used. The works also utilized specialized equipment from the Pavlodar oil pipeline management of KazTransOil JSC.


It should be noted that the project for the reconstruction of the «Uzen-Atyrau-Samara» main oil pipeline section is included in the Investment Program of KazTransOil JSC. The goal of the project is to ensure safe and uninterrupted oil transportation while maintaining the efficiency of the production process.
 