Sections of the «Prorva-Kulsary» main oil pipeline with a total length of 16 km were put into operation after reconstruction

23.08.2021    Views: 156
Source: Press service
«KazTransOil» JSC has completed the connection of the newly constructed pipeline of the main oil pipeline «Prorva-Kulsary» on sections on 0-3 km, 21-33 km, 37-38 km with a total length of 16 km.

After the reconstruction, 191 employees of Atyrau, Pavlodar, Karaganda and Mangistau oil pipeline departments of «KazTransOil» JSC carried out work on the commissioning of sections of the main oil pipeline «Prorva-Kulsary». 58 units of special equipment were involved.

This reconstruction of the pipeline of the main oil pipeline «Prorva – Kulsary» was realized in the framework of the project «Capital repair with the replacement of the pipeline «Prorva-Kulsary» on sections 0-3 km, 4-6 km, 9-12 km, 13-15 km, 21-33 km, 37-38 km, 39-43 km, 46-50 km, 60-64 km, 73-76 km, 90-95 km, 100-101 km with start-up camera of cleaning and diagnostics means» (1st and 2nd line).

The main oil pipeline «Prorva-Kulsary» was put into operation in 1986, connected to the main oil pipeline «Ozen - Atyrau – Samara» for transportation of oil fields Atyrau region for export and the internal market. It has a length of 103 km, a design capacity of 7.01 million tons of oil per year, and an actual capacity of 3.4 million tons of oil per year.  
For reference:

«KazTransOil» JSC – the national operator of the main oil pipeline. It is part of the «NC «KazMunayGas» JSC Groups. Owns a diversified network of main oil pipelines with a length of 5.4 thousand km. It transports oil to Kazakhstan refineries and for export in the following directions: Atyrau-Samara section of the Uzen-Atyrau-Samara trunk oil pipeline, transshipment to the «Kazakh-Chinese Pipeline» LLP system (Atasu-Alashankou oil pipeline), Aktau port (oil loading into tankers), transshipment to the Caspian Pipeline Consortium-K JSC system, oil loading into railway tanks at the Shagyr Oil Refinery and the T. Kasymova. The production facilities of «KazTransOil» JSC are located in Mangistau, Atyrau, West Kazakhstan, Aktobe, Pavlodar, Karaganda, Turkestan, North Kazakhstan regions, Nur-Sultan, Almaty and Shymkent.

Public Relations and Internal Communications Department
of KazTransOil JSC