KZTO 839,00 (-0,27%)
Shares of KazTransOil JSC (KASE) 839,00 (-0,27%)
Brent ()
WTI ()
0
0
0

Completion of work on connection of 50 km section of the Astrakhan-Mangyshlak main water pipeline after reconstruction

 11.07.2022    1621
KazTransOil JSC group of companies completed the connection of the newly built section at 449-499 km of the Astrakhan-Mangyshlak main water pipeline after reconstruction.

Commissioning of a 50 km section of the water conduit was carried out by Kulsary, Mangistau and Atyrau oil pipeline departments of KazTransOil JSC. The reconstruction will increase the reliability of the pipeline network of the Astrakhan-Mangyshlak main water pipeline and ensure uninterrupted water supply for consumers in Atyrau and Mangystau regions.

In view of the prospective growth in the volume of water consumption in the western region of Kazakhstan, as well as in order to upgrade worn-out equipment, the Main Waterline LLP is implementing the «Reconstruction and expansion of the Astrakhan-Mangyshlak main water pipeline» investment project. As a result, the water pipeline capacity will increase to 170,000 cubic meters per day.
 
Public Relations and Internal Communications Department,
KazTransOil JSC
Reaction:
Partners