KazTransOil JSC summed up the production results for 2024. In the reporting period, the planned indicators for the transportation and cargo turnover of oil were fulfilled.
The volume of oil transportation through the main oil pipeline system of KazTransOil JSCamounted to 44 million 887 thousand tons of oil, which is 699 thousand tons more than in 2023.
The volume of oil supplies to domestic oil refineries of the Republic of Kazakhstan - Atyrau Oil Refinery LLP, PetroKazakhstan Oil Products LLP, Pavlodar Petrochemical Plant LLP in 2024 amounted to 16 million 712 thousand tons (5 million 519 thousand tons, 5 million 734 thousand tons, 5 million 459 thousand tons, respectively), which is 139 thousand tons more than in 2023.
The volume of oil transportation to the refinery JV CASPI BITUM LLP amounted to 655 thousand tons.
The volume of oil transportation via the Atyrau - Samara section of the Uzen - Atyrau - Samara main oil pipeline amounted to 10 million 378 thousand tons, which is equivalent to the level of the same period in 2023.
The section of the TON-2 oil pipeline located in the Republic of Kazakhstan transported 11 million 808 thousand tons of oil, which is 566 thousand tons more than in 2023.
11 million 190 thousand tons of oil were transshipped into the Atasu-Alashankou main oil pipeline, which aligns with the level of the same period in 2023.
The volume of oil transshipped into the system of Caspian Pipeline Consortium-K JSC amounted to 4 million 208 thousand tons, which is 967 thousand tons more than in 2023.
Oil loading into tankers in the port of Aktau using the capacities of KazTransOil JSC amounted to 3 million 360 thousand tons, which is consistent with the level of the same period in 2023.
Oil cargo turnover via the main oil pipeline system of KazTransOil JSC amounted to 35 billion 526 million ton-kilometers, which is 1 billion 318 million ton-kilometers higher than the 2023 figure.
The consolidated oil cargo turnover of KazTransOil JSC amounted to 45 billion 176 million ton-kilometers, which is 1 billion 392 million ton-kilometers higher than the 2023 figure.
18 million 789 thousand tons of oil were transported via the oil pipeline system of Kazakhstan-China Pipeline LLP, which is in line with the same period in 2023. Oil cargo turnover amounted to 16 billion 858 million ton-kilometers, which is also at the level of the same period in 2023.
The volume of oil transportation via the oil pipeline of NWPC MunaiTas LLP amounted to 5 million 791 thousand tons, which is 264 thousand tons higher than in 2023. Oil cargo turnover amounted to 2 billion 395 million ton-kilometers, which is 159 million ton-kilometers higher than in 2023.
Across the Batumi Oil Terminal LLC group of companies, the volume of oil, oil products and gas transshipment amounted to 1 million 856 thousand tons, which is 282 thousand tons higher than in 2023.
26 million 495 thousand cubic meters of fresh water were supplied to consumers in the Atyrau and Mangistau regions of Kazakhstan via the Astrakhan - Mangyshlak water pipeline of Main Waterline LLP, which is 1 million 409 thousand cubic meters higher than in 2023. m less than in the same period in 2023.